Chad and Sandra's
Home Building Page
Links to Other Pictures:
Pictures of the Surrounding Area
Pictures of Appliances/Fixtures
Pictures of Construction Site
High Water After Hurricane Frances
Abstract House Art
Pictures of Dave & Lisa's House
Framing Sub-contractors
July 14, 2005
House Plan Links:
Dream Home Source - House Plan
Countdown Clock
Pictures of the Plan built in other locations
Weekly Updates on Construction Progress
This page has pictures of the house building in Charlotte at Various Stages:
Week 48 - Move -in 7/4
Week 47 - Appliances & Landscaping 6/27
Week 46 - Carpet & Cleaning 6/20
Week 45 - Door Handles 6/13
Week 44 - Island Complete 6/6
Week 43 - Appliances & Mirrors 5/30
Week 42 - Finishing Tile & Floor 5/23
Week 41 - Driveway and Deck 5/16
Week 40 - Faucets and Sinks 5/9
Week 39 - Tubs, Counters, Steps 5/2
Week 38 - Cabinets 4/25
Week 37 - Cabinets & Retaining Wall 4/18
Week 36 - Light Fitxtures 4/11
Week 35 - Stucco, Paint and Septic 4/4
Week 34 - Stucco Painted 3/28
Week 33 - Stucco, Paint and More Tile 3/21
Week 32 - Painting and Tile Start 3/14
Week 31 - Stairs, Prepare for Stucco 3/7
Week 30 - Boxing Completed 2/28
Week 29 - Paint and Tile Prep 2/21
Week 28 - Brick and Trim 2/14
Week 27 - Doors, Hardwood and Trim 2/7
Week 26 - Brick is Started 1/31
Week 25 - Finishing Dry wall 1/24
Week 24 - Dry Wall and Finishing 1/17
Week 23 - Insulation and Dry Wall 1/10
Week 22 - Prepare for Drywall 1/3
Week 21 - Inspection Fixes 12/27
Week 20 - Structured Wiring 12/20
Week 19 - All Rooms 12/13
Week 18 - Electric, Plumbing and HVAC 12/6
Week 17 - Framing 99% Complete 11/29
Week 16 - Roof and Windows 11/22
Week 15 - Finishing Exterior Walls and Roof 11/15
Week 14 - Backfilling and More Framing 11/8
Week 13 - Framing the Roof 11/1
Week 12 - Started framing the Roof 10/25
Week 11 - Framing Stairs and Upstairs 10/18
Week 10 - Framing Main Floor and Upstairs 10/11
Week 9 - Framing Main Floor and Basement 10/4
Week 8 - Basement floor and First Walls 9/27
Week 7 - Basement ready for floor 9/20
Week 6 - Basement walls are poured 9/13
Week 5 - Footers are Poured 9/6
Week 4 - Digging the footers 8/30
Week 3 - Digging the well 8/23
Week 2 - Digging the basement 8/16
Week 1 - Clearing the lot 8/9
Week 0 - Before Construction Started 8/2